For a new build with screed across the whole ground floor: 110 litres a day, for rooms up to about 600 m³.
View this unitOupeye lies in the Basse-Meuse, north of Liège. The municipality runs from the Meuse up onto the plateau towards the Hesbaye, with the Albert Canal and its business parks in between. We drive there in just over an hour.
OupeyeThe right price starts with what needs to dry. For a whole house, wet screed or plasterwork you calculate a complete drying package; for a single room, a single unit may be suitable. Delivery in Oupeye is included in your drying package.
You hire a drying package calculated on the volume, the material and the temperature of your site. The price is known in advance and covers delivery, installation, the moisture reading at the start and at handover, and collection. Not dry within the calculated period? Then the hire continues free of charge, under the terms.

You don't need to combine units yourself. We calculate your drying package based on the floor area, the material and the layer thickness. You see the package price in advance, including delivery to postcode 4680, installation, readings before and after, and collection.
A calculated set-up for your floor, matched to the thickness of the screed. The final reading helps you and your floor layer decide when finishing can start.
More about this dryingConstruction dehumidifiers and fans for even drying throughout the house. We choose the capacity and spread the units over the rooms.
More about this dryingA leak or a flood? Have the cause repaired and standing water removed first. We assess the wet materials and match the drying to them.
More about this drying100% drying guarantee included. Is the material still not dry within the calculated period, despite correct drying conditions? Then you keep hiring the units free of charge, under our drying guarantee terms. This applies to calculated packages that we deliver and install; single units for collection are not covered.
No deposit. The calculator shows your total price and the extras you choose yourself, such as a condensate pump, extra heating or an official moisture report.
Oupeye has seven villages. Hermalle-sous-Argenteau, Haccourt and Vivegnis lie in the valley. Hermée, Heure-le-Romain and Houtain-Saint-Siméon lie on the plateau, and Oupeye itself lies in between.
In the villages along the Meuse stand older houses in brick and natural stone, often without a damp-proof course in the wall. After a new floor or new plasterwork they dry more slowly than a new build. Thick walls release their moisture slowly, and the ground floor stays cool.
On the plateau around Hermée and Houtain, housing estates with detached homes have been added. There the moisture comes mainly from a fresh screed and new interior walls. That water has to come out before the parquet or tiles are laid.


For a new build with screed across the whole ground floor: 110 litres a day, for rooms up to about 600 m³.
View this unit
This radial fan blows in a targeted way over a fresh screed, so the corner by the patio door dries too.
View this unit
For a village house in Haccourt or Hermalle being renovated floor by floor: 70 litres a day.
View this unit
This 20 kW site heater warms up a cold ground floor in the valley, so the condensation dehumidifier works better. It needs 400 V.
View this unitVia the E313 we are in Oupeye in just over an hour. You choose a delivery date when you book, and we fix the delivery time with you by appointment. The technician places the units, sets them up and takes a reading at the start. If the street on your housing estate has not been laid yet, let us know in advance.
Aartselaar is just over an hour from Oupeye. If you collect a unit and return it later, you make that drive four times. A construction dehumidifier also has to be transported upright. So collecting mainly pays off if you regularly drive towards Antwerp anyway.
Boomsesteenweg 12, Unit 11, 2630 Aartselaar
Mon–Fri 08:00–17:00, by appointment
Sites in the province of Liège, each with photos of the site itself. The same team, the same reading at the start and at handover.
The table helps you plan the hire period. A guide time does not confirm that the material is dry enough. The check before finishing is still needed.
| What needs to dry | Without a dehumidifier | With a Vernast drying package |
|---|---|---|
| Cement screed 5 cm | 6 to 9 weeks | 2 weeks |
| Cement screed 6 cm | 8 to 12 weeks | 3 weeks |
| Cement screed 7 cm | 10 to 15 weeks | 4 weeks |
| Plasterwork 1 cm | 1 to 2 weeks | 2 weeks |
| Plasterwork 2 cm | 2 to 4 weeks | 3 weeks |
| Plasterwork 3 cm | 3 to 6 weeks | 4 weeks |
The table gives guide values for planning. The actual drying time depends on the material and the conditions on site. Before finishing, have the residual moisture checked against the requirements of your floor layer or decorator. For calculated packages, free continued hire applies under the drying guarantee terms. How long screed needs to dry explains it case by case.
We deliver in Oupeye and the surrounding municipalities. Choose a place below for details on hire and delivery, or see our service area in the province of Liège.
Delivery to Ans, Awans, Aywaille and the other places below. Choose your municipality for details on hiring a dehumidifier.
See for each municipality how to hire a construction dehumidifier, what a drying package includes and how to arrange delivery.
From your request to collection. We agree the installation, explain how to use the units and follow the drying process with moisture readings.
Calculate your package online or call us for advice. Give us your site address, your preferred start date and the dimensions of the rooms.
At the agreed time the technician installs the units, connects the condensate drain and explains how to use them.
Use the set-up as the technician explained. Check the condensate drain and report any faults or new moisture problems.
We check the moisture and arrange collection. For calculated packages, free continued hire applies if the drying guarantee terms are met.
Read how customers experience Vernast's delivery, appointments and follow-up. These reviews are about our service across our whole service area.
“Snelle respons en dezelfde dag nog een droger geïnstalleerd. Top service!”
“Zeer goede service en flexibiliteit. Werken zijn uitstekend uitgevoerd. Vriendelijk personeel. Firma zeker aan te raden.”
“We zijn bijzonder tevreden. Het personeel is professioneel én vriendelijk. Het werk is grondig uitgevoerd. Bovendien werd het achteraf goed opgevolgd.”
Our drying experts will help you straight away, with advice tailored to your situation.
As a rule of thumb, without help you allow a week per centimetre for the first four centimetres, and longer after that. With a large dehumidifier, closed windows and a fan over the floor it goes faster. Have the residual moisture measured before the parquet layer starts.
Old walls of brick or natural stone are thick and often have no damp-proof course. They hold a lot of water and release it slowly, especially if the ground floor is cold. A dehumidifier with a site heater and enough time works better there than a short drying session.
Yes, if the van can drive safely to close to the home. Describe the access when you book. The technician does the last stretch across the site with a sack truck.
For a ground floor with screed, one large dehumidifier with a fan is often enough. If there is new plasterwork upstairs too, put a second dehumidifier there. We calculate on the volume of the room, not just the floor area.
Installed and set up by our technician, with a moisture reading at the start and at handover. Prefer to talk it through first? Feel free to call us.