Every new build contains construction moisture: mixing water from the screed, the plaster coat, the masonry and the concrete. That water has to leave the building before the floor layer, the decorator and your removal van arrive. There are two ways to go about it. You let the house dry on its own, or you control the indoor climate with a construction dehumidifier. Below: what the first approach really asks of you, why the season decides, and what the difference is in weeks.

This is not about a puddle on the floor. A 6 cm screed over 120 m² is well over seven cubic metres of mortar, and the mixing water the cement does not bind chemically has to come back out through the surface. Then there are the walls, the shell and the finishing on top of that. All that water leaves the building by one route: the indoor air.
The biggest reservoir, and the slowest. The water at the bottom has to travel up through the full thickness, because the insulation seals off everything below.
Thin, but on every wall and ceiling in the house. It gives up its water quickly, and all of it ends up in the same indoor air.
The shell has stood in wind and rain for months. Clay block and concrete take up water and then slowly release it into the space again.
Tile adhesive, filler, poured floors and paint bring in water all over again, just when the building is closed and nothing can get out any more.
Everything those layers give off first hangs in the indoor air. If that air does not leave the building, the moisture simply soaks back in somewhere else.
Natural drying is not a matter of waiting, it is a method: heating and ventilating, every day. It only works when these conditions come together. If one is missing, that one sets the pace for the whole.
Warm air carries far more water than cold air. In an unheated shell at five degrees, drying all but stops, however long you wait.
Air that is already full of moisture takes up nothing more. As long as the indoor air stays saturated, the screed cannot get rid of its water.
Just above a floor and against a wall, a layer of saturated air lingers. Without movement, that layer insulates the surface from the rest of the room.
The moisture has to leave the building. If it stays inside, it condenses on the coldest surface it can find: the glass, the sill, the corner behind the cupboard.
The four above determine how much time you need. If one cooperates and the rest do not, the slowest sets the pace.
Air can only carry a certain amount of water, and the warmer it is, the more that can be. That one fact explains why the same home dries faster in January than in July, as long as you keep the heating on.
In winter, outside air is bone dry as soon as it warms up. Air at 5 degrees with 90 percent relative humidity carries little water. Let it in and warm it to 20 degrees, and its relative humidity drops to around 35 percent. Air like that eagerly takes up moisture, and with the next round of ventilation that moisture goes outside with it.
In summer, the same mechanism works against you. Outside air at 20 degrees with 80 percent humidity is already fairly full. Let into a home at 22 degrees, it ends up at around 70 percent, and then there is little room left to take up moisture. Ventilating feels good but achieves hardly any drying.
And in a closed-up, unheated shell, nothing happens. Inside and outside are equally cold, the air is still and saturated. The home does not dry slowly, it simply does not dry. That is the state most sites are in in November.
| Situation | Indoors after warming | What ventilating achieves |
|---|---|---|
| Winter, heated | ± 35% | Strong drying, as long as you keep heating |
| Spring or autumn | 45 to 65% | Dries in fits and starts; a wet week sets it back |
| Summer, warm and humid | ± 70% | Little to nothing; sometimes you bring moisture in |
| Closed shell, no heating | 80% and more | Drying all but stops |
On the left, what the screed needs on its own in a favourable indoor climate; on the right, the hire period we allow for that thickness in our packages. That difference is not a promise about your floor, it is the difference between waiting and taking control.
The bars are on the same scale, with the slowest drying at 100 percent. The guide figure follows the usual rule of thumb for sand and cement screed in a ventilated space at around 20 degrees.
| What is drying | Natural (guide figure) | With a drying package |
|---|---|---|
| Screed, 5 cm | ± 6 weeks | 2 weeks |
| Screed, 6 cm | ± 8 weeks | 3 weeks |
| Screed, 7 cm | ± 10 weeks | 4 weeks |
| Plaster, 1 cm | 1 to 2 weeks | 2 weeks |
| Plaster, 2 cm | 2 to 4 weeks | 3 weeks |
| Plaster, 3 cm | 3 to 6 weeks | 4 weeks |
| Screed and plaster together | The slower of the two | 4 weeks |
The difference is not just speed. Natural drying depends on the weather, on how you heat and on who opens the windows that day. A drying package turns it into a controlled, measurable process.
Drying is not just a question of patience. As soon as work carries on over construction moisture, the problem moves into layers where you only see it again a season later.
Parquet, vinyl and a poured floor seal off the screed. If there is still moisture underneath, it has nowhere to go and comes back as cupped boards or lifting strips.
Paint will not stay put on a plaster coat that is still wet inside. The result is dull patches, blisters or a layer that comes loose after a year.
Moisture condenses where it is coldest: behind cupboards, in the corner of an external wall, on the sills. That is where the black growth starts, and it does not go away on its own.
Misted-up windows, a musty smell and washing that will not dry. Anyone who moves into a wet house spends months heating water instead of their home.
The floor layer and the decorator have diaries. If you give up your slot because it is not dry yet, you go to the back of the queue, and that often costs more weeks than the drying itself.
Not every site needs a construction dehumidifier, and we would rather say so here than after you have paid. Natural drying is a good choice when these things come together.
If one of those points does not apply, a drying package buys you certainty rather than speed: a timescale you can pass on and a reading that confirms it. If you only want the units and set them up yourself, that is possible too, at the collection rate from our depot along the A12.
| Your situation | The approach that fits |
|---|---|
| No date to meet, summer | Natural drying: heat and ventilate |
| Only plaster, thin coat | Often natural, certainly in a lived-in house |
| The floor layer is booked | Drying package with readings and an end date |
| Closed shell, winter, 7 cm screed | Drying package, with a site heater on a cold site |
| You would rather set up yourself | Individual units at the collection rate |
Our drying experts will help you straight away, with advice tailored to your situation.
There is no fixed timescale, and that is exactly the problem. For the screed, usually the slowest layer, building practice allows roughly one week per centimetre for the first four centimetres and then roughly two weeks for each extra centimetre: at 6 cm that comes to around 8 weeks. That guide figure only applies in a heated and ventilated space at around 20 degrees. On a closed-up, unheated site in November it does not run more slowly; it barely runs at all. That is why nobody commits to an end date without measuring.
That is the natural method, and it really does work, provided you do both at the same time. Ventilating alone cools the building down, and cold air carries little moisture away. Heating alone drives the moisture out of the materials but keeps it in the house, where it condenses again on the first cold surface. The combination works best in winter: outside air at 5 degrees and 90 percent humidity becomes, once warmed to 20 degrees indoors, air at around 35 percent, and that takes up water eagerly. Only then you do pay for the heat that escapes with every round of ventilation.
No, quite the opposite. A condensation dehumidifier works in a closed space: it draws in the indoor air, cools it until the water condenses out, drains that water away and blows the air back into the room dry and slightly warmed. If the windows are open, you keep bringing in fresh damp air and the unit is effectively drying the street. So keep doors and windows closed, and let the unit run day and night.
For a 6 cm screed, the guide figure for natural drying is around 8 weeks in favourable weather, against 3 weeks with a drying package. With plaster the difference is smaller in weeks but just as unpredictable: a 1 cm coat is dry in 1 week in a ventilated, heated home and still not dry after a month on a closed, cold site. So the real difference is not just the duration, but that a drying package comes with a date.
You can, but you then take the moisture into your daily life: misted-up windows, a musty smell, cupboards against external walls with mould growing behind them, and a heating bill that mainly warms up water. More annoying is what happens under your floor and behind your paint, because you only see that a season later. If you do move in, keep heating and ventilating well, and lay sensitive floor finishes as late as possible.
A condensation dehumidifier performs best roughly between 15 and 25 degrees; below that its output drops because there is less water in the air to condense. On a cold site we therefore add an electric site heater with a thermostat, or we choose a desiccant dehumidifier, which works with a drying agent and keeps removing moisture even at low temperatures. Which unit suits when is explained in our guide to condensation and desiccant dehumidifiers.
By measuring, not by looking. A screed that is hard and light in colour can still be wet inside, and a wall that feels dry is only dry in its outer few millimetres. We record the residual moisture at the start and again at handover; those two values are what an end date rests on. If your floor layer or your building file needs a signed report, an official moisture report can be added.
That depends on the volume of your home and on what needs drying: those two determine how many units are needed and how long they stay. The drying calculator asks for your floor area, the screed thickness and what you are drying, and immediately shows the package with the price, including delivery, installation and the readings. All individual daily and weekly rates are on our prices page.
Then these two pages pick up where this guide leaves off: with the timescales per layer and with what happens on your site.
The guide figures per centimetre, the difference between cement and anhydrite screed, the heating-up protocol for underfloor heating and when to measure residual moisture.
Read the screed guide →What drying on a new-build site costs and how it works: one package, one hire period and one reading before and after.
See drying in new builds →The calculator turns your volume into a package with the right units and the right hire period. Our technician sets up, adjusts and measures at the start and at handover. If it is not dry by then, we extend free of charge.
Calculate your drying package
Tell us what is drying, when it needs to be ready and what state your site is in. You will get an honest answer within one working day, even if that answer is that you do not need anything.