Performance construction dehumidifier
For a terraced house on the slope with new plasterwork: 70 litres a day, for rooms up to about 400 m³.
View this unitBeyne-Heusay lies just east of Liège, on the slope from the Meuse valley up to the Herve plateau. The municipality joins on to Jupille and Grivegnée, so you often do not notice where Liège ends. We get there from Aartselaar in just over an hour.
Beyne-HeusayThe right price starts with what needs to dry. For a whole house, wet screed or plasterwork you calculate a complete drying package; for a single room, a single unit may be suitable. Delivery in Beyne-Heusay is included in your drying package.
You hire a drying package calculated on the volume, the material and the temperature of your site. The price is known in advance and covers delivery, installation, the moisture reading at the start and at handover, and collection. Not dry within the calculated period? Then the hire continues free of charge, under the terms.

You don't need to combine units yourself. We calculate your drying package based on the floor area, the material and the layer thickness. You see the package price in advance, including delivery to postcode 4610, installation, readings before and after, and collection.
A calculated set-up for your floor, matched to the thickness of the screed. The final reading helps you and your floor layer decide when finishing can start.
More about this dryingConstruction dehumidifiers and fans for even drying throughout the house. We choose the capacity and spread the units over the rooms.
More about this dryingA leak or a flood? Have the cause repaired and standing water removed first. We assess the wet materials and match the drying to them.
More about this drying100% drying guarantee included. Is the material still not dry within the calculated period, despite correct drying conditions? Then you keep hiring the units free of charge, under our drying guarantee terms. This applies to calculated packages that we deliver and install; single units for collection are not covered.
No deposit. The calculator shows your total price and the extras you choose yourself, such as a condensate pump, extra heating or an official moisture report.
The municipality consists of Beyne-Heusay, Queue-du-Bois and Bellaire. Like much of the Liège fringe, it has a coal-mining past. The mines are closed, but terraced houses from that time still shape the streets, with newer neighbourhoods and flats in between.
Many older homes stand on the slope, with a cellar or semi-basement on the low side. At the back the ground is then higher than the floor, and after a wet winter moisture seeps through the wall there. During a renovation you need to know which moisture is construction moisture and which comes from outside.
In the newer neighbourhoods stand flats and family homes. There the moisture comes mainly from fresh screed and new plasterwork. A flat has little volume and little air exchange, so the water lingers in the room.


For a terraced house on the slope with new plasterwork: 70 litres a day, for rooms up to about 400 m³.
View this unit
For a semi-basement half in the ground. The desiccant dehumidifier keeps working in a cool, damp room.
View this unit
For a flat with new plasterwork: compact, 50 litres a day, and economical at 0.75 kW.
View this unit
Along the back wall against the slope, this fan carries the wet air towards the dehumidifier.
View this unitVia the E313 and the E40 we are with you in just over an hour. You choose a delivery date when you book; the delivery itself is by appointment. In the sloping streets parking is sometimes awkward. Let us know whether there is room for a van, and the technician will find the shortest way inside.
From Beyne-Heusay, collecting a unit in Aartselaar costs over two hours' driving there and back. If you need to be in Antwerp anyway, you can combine it. Otherwise delivery is simpler, not least because a construction dehumidifier is not easy to carry up a slope.
Boomsesteenweg 12, Unit 11, 2630 Aartselaar
Mon–Fri 08:00–17:00, by appointment
Sites in the province of Liège, each with photos of the site itself. The same team, the same reading at the start and at handover.
The table helps you plan the hire period. A guide time does not confirm that the material is dry enough. The check before finishing is still needed.
| What needs to dry | Without a dehumidifier | With a Vernast drying package |
|---|---|---|
| Cement screed 5 cm | 6 to 9 weeks | 2 weeks |
| Cement screed 6 cm | 8 to 12 weeks | 3 weeks |
| Cement screed 7 cm | 10 to 15 weeks | 4 weeks |
| Plasterwork 1 cm | 1 to 2 weeks | 2 weeks |
| Plasterwork 2 cm | 2 to 4 weeks | 3 weeks |
| Plasterwork 3 cm | 3 to 6 weeks | 4 weeks |
The table gives guide values for planning. The actual drying time depends on the material and the conditions on site. Before finishing, have the residual moisture checked against the requirements of your floor layer or decorator. For calculated packages, free continued hire applies under the drying guarantee terms. How long screed needs to dry explains it case by case.
We deliver in Beyne-Heusay and the surrounding municipalities. Choose a place below for details on hire and delivery, or see our service area in the province of Liège.
Delivery to Ans, Awans, Aywaille and the other places below. Choose your municipality for details on hiring a dehumidifier.
See for each municipality how to hire a construction dehumidifier, what a drying package includes and how to arrange delivery.
From your request to collection. We agree the installation, explain how to use the units and follow the drying process with moisture readings.
Calculate your package online or call us for advice. Give us your site address, your preferred start date and the dimensions of the rooms.
At the agreed time the technician installs the units, connects the condensate drain and explains how to use them.
Use the set-up as the technician explained. Check the condensate drain and report any faults or new moisture problems.
We check the moisture and arrange collection. For calculated packages, free continued hire applies if the drying guarantee terms are met.
Read how customers experience Vernast's delivery, appointments and follow-up. These reviews are about our service across our whole service area.
“Snelle respons en dezelfde dag nog een droger geïnstalleerd. Top service!”
“Zeer goede service en flexibiliteit. Werken zijn uitstekend uitgevoerd. Vriendelijk personeel. Firma zeker aan te raden.”
“We zijn bijzonder tevreden. Het personeel is professioneel én vriendelijk. Het werk is grondig uitgevoerd. Bovendien werd het achteraf goed opgevolgd.”
Our drying experts will help you straight away, with advice tailored to your situation.
The construction moisture, yes, with a desiccant dehumidifier that also works in a cool room. If the ground at the back pushes water through the wall, it will come back. The technician takes readings during installation and tells you whether something needs doing on the outside first.
Yes. For a flat we usually choose the compact model. Put the unit in a room with the door shut, and warn the neighbours if it has to run day and night. It works on a standard socket.
As close to the front door as possible, but a few dozen metres is no problem: the technician has a sack truck. If the street is steep or narrow, mention it when you book. That way he knows in advance where he can stop.
That depends on the thickness and type of plaster, and on the temperature of the wall. A cold wall or a thick layer of lime plaster takes longer. Have the wall measured before you paint, because paint on a wet wall will peel later.
Installed and set up by our technician, with a moisture reading at the start and at handover. Prefer to talk it through first? Feel free to call us.

Briefly describe what needs to dry and how big the room is. A drying specialist will reply within one working day, with a proposal for the right package.