View this unitBütgenbach, Butgenbach in French, lies in the German-speaking East Cantons, on the eastern edge of the High Fens. The municipality is known for the Bütgenbach reservoir on the Warche. Besides Bütgenbach itself, the villages of Elsenborn, Weywertz, Nidrum and Berg belong to it, and near Elsenborn there is a military camp. From Aartselaar it takes about two hours to drive there.
BütgenbachThe right price starts with what needs to dry. For a whole house, wet screed or plasterwork you calculate a complete drying package; for a single room, a single unit may be suitable. Delivery in Bütgenbach is included in your drying package.
You hire a drying package calculated on the volume, the material and the temperature of your site. The price is known in advance and covers delivery, installation, the moisture reading at the start and at handover, and collection. Not dry within the calculated period? Then the hire continues free of charge, under the terms.

You don't need to combine units yourself. We calculate your drying package based on the floor area, the material and the layer thickness. You see the package price in advance, including delivery to postcode 4750, installation, readings before and after, and collection.
A calculated set-up for your floor, matched to the thickness of the screed. The final reading helps you and your floor layer decide when finishing can start.
More about this dryingConstruction dehumidifiers and fans for even drying throughout the house. We choose the capacity and spread the units over the rooms.
More about this dryingA leak or a flood? Have the cause repaired and standing water removed first. We assess the wet materials and match the drying to them.
More about this drying100% drying guarantee included. Is the material still not dry within the calculated period, despite correct drying conditions? Then you keep hiring the units free of charge, under our drying guarantee terms. This applies to calculated packages that we deliver and install; single units for collection are not covered.
No deposit. The calculator shows your total price and the extras you choose yourself, such as a condensate pump, extra heating or an official moisture report.
The High Fens begin just beyond the municipal boundary, and you notice it in the climate: plenty of rain, fog, snow and hard night frost. Around the lake stand holiday homes and flats, and in the villages mainly houses and farmhouses.
Around the reservoir stand holiday homes and second homes that are empty for part of the year. If such a home stayed unheated and shut all winter, the walls are often clammy in spring, the cellar smells musty or there is mould behind the cupboards. When freshening up or renovating, dry the room first and only paint afterwards.
In the villages on the high plateau the ground is wet from the rain and the nearby peat. A cellar or ground floor without a good damp-proof course absorbs that moisture. During a renovation the technician measures whether it is construction moisture or moisture from below. A dehumidifier solves the first; for the second, the wall itself has to be dealt with.


For a holiday home or flat by the lake that is clammy after the winter. A compact dehumidifier that works on a standard socket.
View this unit
For a cold cellar on the wet high plateau. The desiccant dehumidifier keeps working where a condensation dehumidifier falls back because of the cold.
View this unit
For a home being renovated floor by floor, with new plaster and screed. Removes up to 70 litres a day, for rooms up to about 400 m³.
View this unit
First brings an unheated house in Elsenborn up to temperature. At 20 kW it is smaller than the 30 kW heater, but it also needs a 400 V connection.
View this unitFrom Aartselaar we drive about two hours, via Liège and Verviers and then the A27 towards Malmedy. You choose a delivery date when you book, and we agree the delivery time with you. If it is a holiday home where you are not always present, let us know who will open the door. The technician places, sets up and measures in the presence of someone who knows the home.
To our collection point in Aartselaar and back you are on the road for about four hours. If you live in Flanders and have a holiday home by the lake, collecting on the way to the East Cantons can work. Always transport a construction dehumidifier upright.
Boomsesteenweg 12, Unit 11, 2630 Aartselaar
Mon–Fri 08:00–17:00, by appointment
Sites in the province of Liège, each with photos of the site itself. The same team, the same reading at the start and at handover.
The table helps you plan the hire period. A guide time does not confirm that the material is dry enough. The check before finishing is still needed.
| What needs to dry | Without a dehumidifier | With a Vernast drying package |
|---|---|---|
| Cement screed 5 cm | 6 to 9 weeks | 2 weeks |
| Cement screed 6 cm | 8 to 12 weeks | 3 weeks |
| Cement screed 7 cm | 10 to 15 weeks | 4 weeks |
| Plasterwork 1 cm | 1 to 2 weeks | 2 weeks |
| Plasterwork 2 cm | 2 to 4 weeks | 3 weeks |
| Plasterwork 3 cm | 3 to 6 weeks | 4 weeks |
The table gives guide values for planning. The actual drying time depends on the material and the conditions on site. Before finishing, have the residual moisture checked against the requirements of your floor layer or decorator. For calculated packages, free continued hire applies under the drying guarantee terms. How long screed needs to dry explains it case by case.
We deliver in Bütgenbach and the surrounding municipalities. Choose a place below for details on hire and delivery, or see our service area in the province of Liège.
Delivery to Amel, Aubel, Baelen and the other places below. Choose your municipality for details on hiring a dehumidifier.
See for each municipality how to hire a construction dehumidifier, what a drying package includes and how to arrange delivery.
From your request to collection. We agree the installation, explain how to use the units and follow the drying process with moisture readings.
Calculate your package online or call us for advice. Give us your site address, your preferred start date and the dimensions of the rooms.
At the agreed time the technician installs the units, connects the condensate drain and explains how to use them.
Use the set-up as the technician explained. Check the condensate drain and report any faults or new moisture problems.
We check the moisture and arrange collection. For calculated packages, free continued hire applies if the drying guarantee terms are met.
Read how customers experience Vernast's delivery, appointments and follow-up. These reviews are about our service across our whole service area.
“Snelle respons en dezelfde dag nog een droger geïnstalleerd. Top service!”
“Zeer goede service en flexibiliteit. Werken zijn uitstekend uitgevoerd. Vriendelijk personeel. Firma zeker aan te raden.”
“We zijn bijzonder tevreden. Het personeel is professioneel én vriendelijk. Het werk is grondig uitgevoerd. Bovendien werd het achteraf goed opgevolgd.”
Our drying experts will help you straight away, with advice tailored to your situation.
Yes, for moisture that has built up in a closed, unheated home. Heat the home, keep the windows shut and let a dehumidifier run for a week or two. If the mould comes back in the same place, there is a leak or a cold bridge, and a dehumidifier will not solve that.
Someone needs to be there who can open the door and knows the home; a neighbour or a manager is fine. The technician places the unit, sets it up and takes a moisture reading at the start. Agree who will be there when you book, so he knows whose bell to ring.
About two hundred kilometres, a drive of around two hours via Liège, Verviers and the A27. Because it is one of our furthest destinations, we plan the deliveries in the East Cantons together and agree the delivery time with you in advance.
The area around the High Fens gets a lot of rain and the ground is wet. A cellar without a good damp-proof course absorbs that moisture from outside. A dehumidifier removes construction moisture after a renovation, but if the moisture keeps coming back, the technician first looks for the cause.
Installed and set up by our technician, with a moisture reading at the start and at handover. Prefer to talk it through first? Feel free to call us.

Briefly describe what needs to dry and how big the room is. A drying specialist will reply within one working day, with a proposal for the right package.