A cement screed of 5 to 7 cm dries on its own in about 6 to 10 weeks. With a construction dehumidifier, we work on 2 to 4 weeks for those thicknesses. What it comes to in your case depends on the thickness, the type of screed, the temperature and the ventilation. Below you will find the guide figures per thickness, the difference with and without a dehumidifier, and how to tell when the floor layer can come in.

For cement screed drying on its own, the building trade has an old rule of thumb: roughly one week per centimetre for the first 4 cm. Beyond that it is considerably slower; allow roughly two weeks for each extra centimetre. A 7 cm floor therefore does not take 7 weeks but about 10.
That is not down to the amount of water alone, but to the route it has to take. Beneath the screed lie insulation and a concrete structural slab; nothing gets through those. The moisture in the bottom layer therefore has only one way out: upwards, through the full thickness of the floor. The thicker the screed, the longer that route, and the more slowly the last centimetres give up their water.
These guide figures apply to a heated, ventilated building at around room temperature. On a cold, closed-up winter site it easily takes longer, because the air above the floor can no longer absorb the moisture. Why that is the case is explained in detail on how drying works.
The moisture cannot escape downwards. That is why every centimetre beyond the fourth costs about two weeks instead of one, and why dry, moving air above the floor helps so much.
On the left, what the floor needs to dry on its own; on the right, the hire period we allow for that thickness in our packages. The difference is not a promise about your floor, but the difference between waiting and controlling the climate.
The bars are on the same scale, with the longest drying time at 100%. The same figures appear in the table below.
| Screed thickness | Natural drying (guide figure) | With a dehumidifier (Vernast package) |
|---|---|---|
| 5 cm | ± 6 weeks | 2 weeks |
| 6 cm | ± 8 weeks | 3 weeks |
| 7 cm | ± 10 weeks | 4 weeks |
A fresh screed goes through two phases, and they ask the opposite of you. First the cement still needs the water; only after that can it come out.
Cement binds water chemically while it cures. Aggressive drying in this phase draws out water the mix still needs: the top shrinks, the bottom does not, and that shows up as cracks or curling edges. Your screed fitter will tell you from which day you can start drying.
Days to weeks, depending on the mixNow the actual drying begins, and it can carry on day and night. A construction dehumidifier keeps the humidity low, and a fan makes sure that dry air really sweeps across the floor. Every hour the unit stands idle lets the moisture soak back into walls and floor.
The weeks from the table aboveFive things decide whether you stay close to the guide figure or go weeks beyond it. You can control four of them yourself.
The biggest factor. The moisture in the bottom layer has to travel up through the full thickness; beyond 4 cm that adds up quickly.
Warm air can hold far more moisture than cold air. Below ten degrees or so, drying all but stops.
If the air in the building is already full of moisture, the screed cannot give off any more, however long you wait.
A layer of saturated air lingers above a floor. A fan sweeps it away, so dry air can pick up the moisture.
Tiles tolerate more residual moisture than parquet, vinyl or a poured floor. The finish determines what you are drying towards.
The drying times above are for sand and cement screed, the most common floor in Belgium. If anhydrite has been laid, different instructions apply, and the manufacturer's override any rule of thumb.
If there is underfloor heating beneath the screed, it is a useful aid to drying, but only if handled with care. This is the shape a heating-up protocol takes; the exact temperatures and days come from your screed fitter or the manufacturer.
A screed that is hard and light in colour can still be wet inside. Under parquet, vinyl or a poured floor, that moisture is then trapped, and it comes back as cupped boards, lifting strips or stains.
Our drying experts will help you straight away, with advice tailored to your situation.
As a guide, a 5 cm cement screed dries on its own in about 6 weeks, and even then only in a building that is heated and ventilated. With a construction dehumidifier, we work on a hire period of 2 weeks for that thickness, including a moisture reading at the start and at handover. Five centimetres is the thinnest screed in our packages and the quickest to dry: the rule of thumb of one week per centimetre still largely holds here. Bear in mind: the calendar does not decide whether the floor is ready, the moisture reading does. A cold or closed-up site can easily run weeks beyond this guide figure.
As a guide, a 6 cm cement screed dries on its own in about 8 weeks, and even then only in a building that is heated and ventilated. With a construction dehumidifier, we work on a hire period of 3 weeks for that thickness, including a moisture reading at the start and at handover. Six centimetres is the most common thickness in a Belgian new build. The two extra centimetres beyond four count double, and that explains the difference with a 5 cm floor. Bear in mind: the calendar does not decide whether the floor is ready, the moisture reading does. A cold or closed-up site can easily run weeks beyond this guide figure.
As a guide, a 7 cm cement screed dries on its own in about 10 weeks, and even then only in a building that is heated and ventilated. With a construction dehumidifier, we work on a hire period of 4 weeks for that thickness, including a moisture reading at the start and at handover. At seven centimetres, waiting on the weather gets really expensive: this is the thickness where natural drying can swallow an entire construction holiday. Bear in mind: the calendar does not decide whether the floor is ready, the moisture reading does. A cold or closed-up site can easily run weeks beyond this guide figure.
Not straight away. Cement screed binds water chemically while it cures, and in that first phase it still needs that water. Ask your screed fitter from when you can start drying actively; that is a matter of days to weeks, depending on the mix and what is in it. Switch the dehumidifier on too early and too hard, and the top dries out while the bottom is still wet, which leads to shrinkage, cracks and, in the worst case, a floor that comes loose. After that, the unit can run day and night: every hour it stands idle lets the humidity climb again.
Yes, and it is the risk people underestimate. If only the surface dries, the top shrinks while the bottom is still swollen with moisture; that tension comes out as cracks or curling edges. That is why a construction dehumidifier does not dry as hard as possible, but towards a target value the technician sets, and why you do not turn the underfloor heating up to full power straight away. A controlled drying process with a reading before and after is faster and safer than a floor you try to force in a week.
Yes, but only by following a heating-up protocol: start gently at a low flow temperature, raise it by one step a day up to the maximum the manufacturer allows, hold it for a few days and then bring it down just as gradually, and all of that only after the waiting time the screed fitter prescribes. Never turn the heating up in one go. And remember that heating only drives the moisture out of the floor, not out of the building: without a dehumidifier or ventilation it condenses on windows, sills and external walls. Completing a heating-up protocol is not proof that the floor is dry either; that still takes a moisture reading.
By measuring, usually with a CM test (carbide method) on a sample taken from the full depth of the floor. A surface meter tells you too little: a screed that is hard and light in colour can still be wet inside. Which limit applies depends on the type of screed, the underfloor heating and the floor finish; tiles usually tolerate more residual moisture than parquet, vinyl or a poured floor. Your floor layer sets that limit, so ask in advance which value they want to see; then you know what you are drying towards. Our drying packages include a reading before and after, and a measurement report on request.
By controlling the climate in the building instead of waiting. Three things at once: heat, so the air can hold more moisture; a construction dehumidifier, which continuously removes that moisture from the air; and air movement, so the saturated layer above the floor is swept away and dry air can get in. Let the unit run day and night and keep windows and doors closed; you are drying the room, not the street. What does not work: only heating, only ventilating when it is damp outside, or switching the dehumidifier off at night to save electricity.
That depends on the volume of the room, not just the floor area: a high open-plan space needs more than a low one. That is why the drying calculator asks for your floor area, what you are drying and the thickness, and then puts together a package with the right number of units and hire period. One undersized unit in a large space will not dry faster if you leave it longer; it simply never reaches the target value. If in doubt, give us a call: a misjudged package costs you weeks, and those weeks cost more than the unit.
No, keep them closed. A construction dehumidifier dries the air in an enclosed space; if a window is open, you keep letting in fresh, damp outside air and the unit carries on drying that instead of your floor. Ventilating only helps when the outside air is drier than the air indoors, and in a Belgian winter or a rainy autumn that is rarely the case. Also close the doors to parts of the building that are not being dried, and keep the dehumidifier in that closed-off space.
Anhydrite screed (based on calcium sulphate) is poured as a liquid and is therefore often thinner and flatter, which works in its favour. On the other hand, it is more sensitive to moisture and usually needs a lower residual moisture level before it can be covered; often the top layer also has to be sanded before it can dry and bond properly. So always follow the instructions of the installer and the manufacturer, which differ from product to product and override any rule of thumb. The drying principle stays the same, though: without dry, moving air in the building, nothing leaves the floor.
You can wait, and it costs nothing in hire. What it does cost is time you pay for elsewhere: for a 7 cm screed, it is roughly 10 weeks of natural drying against 4 weeks with a drying package. During those weeks your construction loan keeps running, every following trade is pushed back with it, and the moisture hangs in a closed building where it can cause mould and rising damp in the plasterwork. What is more, waiting is no guarantee: on a cold, closed-up site without ventilation, drying grinds to a halt, however long you wait. That is why we include a reading before and after, and a Drying Guarantee: if the floor is not dry by the end date, we extend free of charge.
Plasterwork has its own timescales and its own pitfalls, and in a new build the floor and walls usually dry together. Two pages that take it further.
The timescales per coat thickness, the difference between gypsum and cement plaster, and why moisture lingers in a closed-up house until it ends up on the windows.
Read the plaster guide →In a new build, floor and walls are wet at the same time. That can be done in one package, with one hire period and one reading before and after.
See drying in new builds →Our technicians set up the units, set the target value and record the residual moisture at the start and at handover. If the floor is not dry by then, we extend free of charge; see the Drying Guarantee.
Calculate your drying package
Not sure whether your screed will be dry in time for the floor layer, or unsure about the thickness and the number of units? Ask your question and a specialist will reply within one working day.