For a new-build home: 70 litres a day per floor, for rooms up to about 400 m³.
View this unitSeneffe is known for its eighteenth-century castle with its park and for its canals: the Brussels-Charleroi Canal and the Canal du Centre both run through the municipality. Near Feluy lies a large industrial zone.
SeneffeThe right price starts with what needs to dry. For a whole house, wet screed or plasterwork you calculate a complete drying package; for a single room, a single unit may be suitable. Delivery in Seneffe is included in your drying package.
You hire a drying package calculated on the volume, the material and the temperature of your site. The price is known in advance and covers delivery, installation, the moisture reading at the start and at handover, and collection. Not dry within the calculated period? Then the hire continues free of charge, under the terms.

You don't need to combine units yourself. We calculate your drying package based on the floor area, the material and the layer thickness. You see the package price in advance, including delivery to postcode 7180, installation, readings before and after, and collection.
A calculated set-up for your floor, matched to the thickness of the screed. The final reading helps you and your floor layer decide when finishing can start.
More about this dryingConstruction dehumidifiers and fans for even drying throughout the house. We choose the capacity and spread the units over the rooms.
More about this dryingA leak or a flood? Have the cause repaired and standing water removed first. We assess the wet materials and match the drying to them.
More about this drying100% drying guarantee included. Is the material still not dry within the calculated period, despite correct drying conditions? Then you keep hiring the units free of charge, under our drying guarantee terms. This applies to calculated packages that we deliver and install; single units for collection are not covered.
No deposit. The calculator shows your total price and the extras you choose yourself, such as a condensate pump, extra heating or an official moisture report.
In Feluy and Arquennes, blue stone was quarried for a long time. You can see it in the houses, with sills, plinths and window surrounds in grey stone. Familleureux and Petit-Rœulx-lez-Nivelles are mainly villages with farmhouses and housing estates. From Aartselaar we drive there in about an hour.
An old village home in Feluy or Arquennes often has a base of blue stone under a brick façade. The blue stone absorbs little water, but the joints and the wall behind it do. That moisture cannot get out through the stone. After a renovation, a wall like that therefore dries mainly inwards, where the dehumidifier stands.
Around Seneffe and Familleureux people are building new homes and extensions. There it is a matter of construction moisture from concrete, screed and plasterwork, which does not come back once dried. With one dehumidifier per floor and a fan across the screed, your floor layer can plan better, even in a wet autumn.


For a new-build home: 70 litres a day per floor, for rooms up to about 400 m³.
View this unit
Across a fresh screed in a new home: this fan blows low across the floor, so the floor layer can start sooner.
View this unit
Against an old wall behind a blue-stone plinth: it keeps the air moving along the surface, so the moisture can escape inwards.
View this unit
For a farmhouse or a large open space in the villages: 110 litres a day, for rooms up to about 600 m³.
View this unitThe drive takes about an hour, via the ring road and the E19 towards Nivelles. You choose a delivery date when you book; the delivery itself is by appointment. On a site in a new housing estate, the technician wants to know who will let him in and whether there is power. He installs the units, sets up the drain and measures the moisture in the screed at the start.
Our warehouse in Aartselaar is about an hour away. Collecting can work for a single unit. A new-build home with a screed dries better with well-distributed units, and the technician sets those up on site.
Boomsesteenweg 12, Unit 11, 2630 Aartselaar
Mon–Fri 08:00–17:00, by appointment
Sites in Hainaut, each with photos of the site itself. The same team, the same reading at the start and at handover.
The table helps you plan the hire period. A guide time does not confirm that the material is dry enough. The check before finishing is still needed.
| What needs to dry | Without a dehumidifier | With a Vernast drying package |
|---|---|---|
| Cement screed 5 cm | 6 to 9 weeks | 2 weeks |
| Cement screed 6 cm | 8 to 12 weeks | 3 weeks |
| Cement screed 7 cm | 10 to 15 weeks | 4 weeks |
| Plasterwork 1 cm | 1 to 2 weeks | 2 weeks |
| Plasterwork 2 cm | 2 to 4 weeks | 3 weeks |
| Plasterwork 3 cm | 3 to 6 weeks | 4 weeks |
The table gives guide values for planning. The actual drying time depends on the material and the conditions on site. Before finishing, have the residual moisture checked against the requirements of your floor layer or decorator. For calculated packages, free continued hire applies under the drying guarantee terms. How long screed needs to dry explains it case by case.
We deliver in Seneffe and the surrounding municipalities. Choose a place below for details on hire and delivery, or see our service area in Hainaut.
Delivery to Braine-le-Comte, Le Rœulx, Manage and the other places below. Choose your municipality for details on hiring a dehumidifier.
See for each municipality how to hire a construction dehumidifier, what a drying package includes and how to arrange delivery.
From your request to collection. We agree the installation, explain how to use the units and follow the drying process with moisture readings.
Calculate your package online or call us for advice. Give us your site address, your preferred start date and the dimensions of the rooms.
At the agreed time the technician installs the units, connects the condensate drain and explains how to use them.
Use the set-up as the technician explained. Check the condensate drain and report any faults or new moisture problems.
We check the moisture and arrange collection. For calculated packages, free continued hire applies if the drying guarantee terms are met.
Read how customers experience Vernast's delivery, appointments and follow-up. These reviews are about our service across our whole service area.
“Snelle respons en dezelfde dag nog een droger geïnstalleerd. Top service!”
“Zeer goede service en flexibiliteit. Werken zijn uitstekend uitgevoerd. Vriendelijk personeel. Firma zeker aan te raden.”
“We zijn bijzonder tevreden. Het personeel is professioneel én vriendelijk. Het werk is grondig uitgevoerd. Bovendien werd het achteraf goed opgevolgd.”
Our drying experts will help you straight away, with advice tailored to your situation.
Blue stone is dense and lets little moisture through. The water in the joints and the masonry behind it cannot escape on the outside and has to dry inwards. A dehumidifier with a fan on the inside of the wall helps, but expect it to take longer than a brick wall.
That depends on the thickness, the type of screed and the temperature. With a dehumidifier and a fan it goes noticeably faster than without. We measure the moisture content at the start and can measure again later, so your floor layer decides on a figure.
Yes, a 230 V socket is enough for the dehumidifiers and the fans. Only the electric site heaters need a 400 V connection. If you are working with a temporary site distribution board, check that it has enough capacity for all the units together.
Yes, we deliver in all the districts of Seneffe. In the old village centres the streets are sometimes narrow. Mention it when you book if there is little room to stop, and the technician will bring a sack truck.
Installed and set up by our technician, with a moisture reading at the start and at handover. Prefer to talk it through first? Feel free to call us.