Construction drying Full renovation Commercial property

Construction drying for a shop

Construction drying · shop

The schedule for renovating this shop was tight. A retail unit cannot stay closed any longer than necessary, yet fresh plaster and screed still had to cure in a controlled way. Vernast therefore opted for targeted construction drying that made the entire building schedule achievable, without disrupting the shop's operations more than needed.

The front of the shop where Vernast carried out accelerated construction drying
Treatment
Construction dryingfast & targeted
Preparation
24 hourssite set up for drying
Works
3 daysplaster & screed work
Drying time
4 daysmatched to the schedule
The project

Gaining speed without compromising on quality

In a commercial property every day counts: the shorter the works, the sooner the shop can reopen. At the same time, that time pressure must never come at the expense of build quality. To reconcile both at this shop, Vernast matched the entire drying process to the short lead time, so that each next phase could start without waiting.

  • Tight building schedule with hardly any margin for natural drying time
  • Fresh plaster and screed that had to cure in a controlled way
  • A shop that had to be ready for customers again as soon as possible
  • Construction moisture that threatened to delay each subsequent finishing phase

Our approach

Based on the moisture values and the building schedule, we put together a targeted drying setup: professional construction dehumidifiers, combined with fans that continuously remove the released moisture. Within 24 hours the site was set up for drying, so the indoor climate was immediately under control and the drying process was matched to the short lead time from day one.

The work, step by step

Preparation, 24 hours. The rooms were screened off and the construction dehumidifiers and fans set up and connected, so the moisture level throughout the property quickly began to fall.

Plasterwork without waiting. As soon as the substrate was dry enough, the plastering could start almost immediately on an even, stable base, giving a clean and consistent result.

Screed work in ideal conditions. The screed work followed shortly after. Thanks to the controlled indoor climate, the screed could cure quickly and evenly into a flat, load-bearing floor.

Continuous monitoring. Throughout the four-day drying time we kept a close eye on the moisture values, so each phase followed seamlessly on the next and the deadline was met.

Behind the scenes

The project in pictures

From the demolition phase to the finished showroom, with the construction dehumidifiers hard at work. Browse with the arrows or pick an image below.

Finished showroom with newly installed black track lighting
1 / 10Finished showroom with newly installed track lighting
Demolition phase in the shop with stripped ceiling and exposed substrate
2 / 10Demolition phase: stripped ceiling and exposed substrate
Smoothly plastered room in the shop, ready for finishing
3 / 10Smoothly plastered room, ready for finishing
Plasterwork in progress with a mobile scaffold in the shop
4 / 10Plasterwork in progress with a mobile scaffold
Construction drying by the screened-off shop window
5 / 10Drying by the screened-off shop window
Construction dehumidifiers and fans drying the shop space at speed
6 / 10Construction dehumidifiers and fans drying the space at speed
Construction dehumidifier at work with a view of the shopfront
7 / 10Construction dehumidifier at work with a view of the shopfront
Drying setup by the entrance during the shop renovation
8 / 10Drying setup by the entrance during the renovation
Monitoring the drying process in the bare, plastered shop
9 / 10Monitoring the drying process in the bare space
Vernast team placing the construction dehumidifiers on site in the shop
10 / 10Our team placing the construction dehumidifiers on site
The result

Delivered on time, without compromise

Why clients choose us

Speed and quality hand in hand

By matching the construction drying exactly to the schedule, plaster and screed work could follow each other without waiting. That way we safeguarded both the tight deadline and the build quality, with our own equipment and our own Vernast team. As a result, a commercial property does not need to stay closed any longer than strictly necessary.

After the works

A dry, even base

The result is a dry, stable and flat surface, perfectly ready for the further finishing and fitting-out of the shop. This project shows how targeted construction drying saves valuable building time without sacrificing the end result.